Determining quantities alone is not enough to produce robust, verifiable construction invoices. Contractors must also provide clear evidence of where, when and under what conditions the work was carried out. On infrastructure projects involving numerous drawing revisions, 3D models, drone surveys and photos captured throughout construction, coordinating this information can require considerable effort.
The Echterhoff Group is therefore piloting a digital workflow that brings together invoicing-related information at an early stage. On the BÜ-Konzeption Velpe project, the construction company uses Infrakit as a central, map-based platform for georeferenced drawings, models, documents and photos. The objective is to capture information in a structured, location-based format during construction, rather than having to search for it when the next interim invoice is prepared.
At Echterhoff, Tobias Farin works across digitalization and invoicing management while also contributing to preconstruction, site management and invoicing. For him, a reliable invoicing process does not begin with the measurement sheet. It starts during estimating and construction planning.
When Design Data Must First Be Prepared for Estimating and Construction
Echterhoff operates across civil engineering, bridge construction and infrastructure construction. According to Farin, its clients include Autobahn GmbH and Deutsche Bahn in particular. In day-to-day project delivery, this means working with different specifications, data catalogues and requirements for BIM models and invoicing documentation.
Using the BÜ-Konzeption Velpe project as an example, Farin demonstrated how early data preparation begins. During the estimating phase, the available information initially consisted of PDF drawings, cross-sections and individual elevation data, but no BIM model that could be used directly. From these source files, he generated a digital existing-ground model and 3D solids for different components and layers. This enabled quantities for activities such as excavation and backfilling to be derived and visualized spatially.
The models alone, however, did not resolve the question of how estimators, site managers and foremen could access the information without specialist modelling software. Farin describes the previous limitation: “Whenever I needed to discuss something with the estimator, we always had to meet at my computer.”

For these use cases, he now creates an Infrakit project, uploads the prepared data and gives the relevant colleagues access. They can view the models, take measurements or open cross-sections themselves without Farin having to guide them through every step.
“Whenever I create quantities or models, I quickly set up an Infrakit project, upload the data and invite the estimator or the relevant contact,” he explains. For a company with several regional offices, this simplifies access across locations: the information no longer remains on the computer of the person who created the model.

A Shared Spatial View of Drawings, Models and Site Conditions
One of the key benefits on the project is the georeferenced presentation of information. Drawings, 3D models, orthophotos and other documents are displayed in their real-world locations. This gives project participants a shared spatial view of the construction project, both on desktop and mobile devices.
For the construction site in Velpe, Farin describes the mobile application as “a small construction site navigation system on your phone.” Site managers and foremen can orient themselves on site, display the relevant drawing and see which component is planned at a specific location. Drawing changes can also be tracked through the revision history. One drawing shown during the webinar had already undergone several revisions, yet the project team could still identify the current version.

The 3D models are used for more than visualization. When a foreman needed to know the required elevation following excavation, Farin provided an adjusted terrain model. Using a predefined alignment or a freely positioned section, the foreman could open a cross-section directly on his smartphone and check elevations and distances.
Estimators can also use simple areas and cross-sections to check approximate quantities without editing the model themselves. “For visualizing our projects, it is already worth its weight in gold,” Farin says, summarizing the current focus.

Structured Photo Documentation Instead of Searching Later
Photo documentation is currently Echterhoff’s most frequently used application. Farin cannot be on the construction site every day. At the same time, many situations relevant to invoicing arise during construction—for example, trial excavations, additional work, unexpected ground conditions or materials placed in temporary storage.
Photos are therefore not simply filed in folders. In Infrakit, they can be georeferenced, assigned predefined tags and supplemented with free-text descriptions. Standardized terminology—for example, for potential variations or specific activities—prevents each participant from using different abbreviations. Filters can then be used to retrieve all images relating to a particular time period, activity or issue.

One example from the project involved paving blocks that, contrary to the original assumption, were not to be removed from site. At a resident’s request, they had to be stored temporarily and reinstalled later. The photos and accompanying description document not only the visible site condition but also the context behind the change.
“All this information is now in Infrakit, and I can retrieve it at any time,” Farin says. This creates a usable information base for site management, invoicing and variation management—provided that the records are consistently classified from the outset.

From Construction Documentation to Interim Invoicing
When preparing an interim invoice, Farin filters the objects and photos captured in the project according to the relevant bill-of-quantities items. Using a trial excavation as an example, he demonstrated how the recording date, location, description and photographic evidence can all be retrieved. He then transfers the selected information to the company’s invoicing software and supplements it with the relevant drawing and quantity calculation.
The result is a measurement sheet that provides clearer spatial and chronological context for the work performed. This is particularly relevant because, in Farin’s experience, almost every measurement record on Deutsche Bahn projects requires supporting documentation. Estimated quantities alone are insufficient; quantities must be plausibly derived and presented in a verifiable form.
Infrakit does not replace specialist measurement and invoicing software. Instead, the platform supports the upstream collection, organization and retrieval of the evidence required for invoicing. Quantity calculations and invoice processing continue to be carried out in the dedicated systems designed for those tasks.
Repeated drone surveys and orthophotos complement this workflow. By comparing data captured at different times, Farin can identify which areas have changed and determine whether a site condition still needs to be measured. 360-degree imagery provides an additional spatial overview. Farin says he now creates these site overviews regularly: “I have become a huge fan of 360-degree photos and now try to provide a brief overview of the construction site every Monday and Friday.”
Introducing Digitalization Step by Step
Echterhoff initially introduced Infrakit on selected pilot projects. Before providing clients with wider access, the company wants to test its internal workflows, folder structures and permissions. This will ensure that there are clear rules governing which data remains internal and which information can be shared with project partners.
As part of the implementation, Farin creates short internal videos demonstrating specific workflows. For him, the key is to explain the benefits from each user’s perspective rather than discussing digitalization in abstract terms: What information does the foreman need on site? What makes the site manager’s job easier? And what documentation will the invoicing team need later?
“A construction site only works when everyone works together—from the invoicing team, site management and estimating through to the machine operator and foreman,” Farin emphasizes. “You have to involve everyone and demonstrate both the benefit for me and the benefit for you.” Communicating as equals is essential.
The Next Step: Better-Connected Systems
The pilot phase also highlights the limits that still affect end-to-end digital workflows. Project information remains distributed across several specialist systems, ranging from invoicing and enterprise software to client platforms and Infrakit. Farin’s objective is therefore not to create another isolated data repository, but to enable reliable information exchange between systems.
Open interfaces and vendor-neutral formats are particularly important to him for models, machine-control data, photos and metadata. Information captured in a structured format during construction should remain available to downstream systems after the project has been completed.
Echterhoff is deliberately taking a step-by-step approach: first stabilizing internal workflows, then involving clients and other project partners more systematically. The practical approach adopted in Velpe demonstrates the principle behind this process. Digital construction invoicing does not begin with the invoice. It begins when drawings, models, quantities and site records are connected in a transparent and traceable way throughout construction.
Read more: Orthophotos, 360° photos and point clouds on one map · Design BIM vs. construction BIM in infrastructure projects · How survey engineers can simplify workflows · Infrakit for contractors
Watch the Webinar: Digital Construction Invoicing in Practice
Would you like to see how Echterhoff uses Infrakit for construction measurement, site documentation and invoicing? In the full webinar, Tobias Farin shares practical insights into the company’s digital workflows—from preconstruction through to interim invoicing.