Infrakit helping to build Jokeri Light Rail

Aug 11, 2021
6 min read
Infrakit helping to build Jokeri Light Rail

At a glance

ContractorYIT
ProjectJokeri Light Rail
LocationHelsinki–Espoo, Finland
Scope25 km light rail between Itäkeskus and Keilaniemi
IntervieweeTomi Mäkelä, Head Surveyor
Infrakit used forModel-based construction; progress photos uploaded by supervisors, employees and excavator operators

Infrakit helping to build Jokeri Light Rail

Jokeri Light Rail is a 25-kilometre rail connection between Itäkeskus in Helsinki and Keilaniemi in Espoo. The city councils of Helsinki and Espoo accepted a project plan in 2016; this served as a basis for planning and beginning the Jokeri Light Rail building project in June 2019. Bus line 550, which runs along the same route, is the busiest in the Helsinki region, and no bus service will be able to cope with its increasing traffic volumes. Jokeri Light Rail will replace bus line 550, currently used by some 40,000 people every day. Jokeri Light Rail is expected to be used for approximately 91,000 trips on weekdays in 2030, rising to 125,000 by 2050. The construction stage of Jokeri Light Rail is expected to be completed in 2023, with traffic commencing on 2024.

A so-called alliance model is being applied to the planning and construction of Jokeri Light Rail, meaning that the customers, designers and contractors create a joint organisation. The customers are the cities of Helsinki and Espoo. Following public tendering, Ramboll Finland Oy, Sitowise Oy and NRC Group Finland Oy were chosen as the designers. The constructors are YIT Oy and VR Track Oy.

Jokeri Light Rail construction site. Photo: Jokeri Light Rail

Tomi Mäkelä from YIT, acting as Head Surveyor in the Jokeri Light Rail project, is also an Infrakit main user. Mäkelä sees plenty of benefits in using Infrakit in this model-based project. “We use a lot of photos in construction. Supervisors, employees and excavator operators upload a steady stream of photos on construction progress into Infrakit. We currently have more than 10,000 photos of the project. This is a big number, which is getting bigger all the time. We create folders for the photos. It’s also been made as easy as possible to add photos to folders.”

Linnoitustie, Espoo Leppävaara, photo: Jokeri Light Rail

Infrakit also makes cooperation easier within the alliance. “HSY can view photographs and completed pipeline networks through Infrakit. Photos provide valuable information on how construction is progressing. Infrakit’s orthophotos have been praised, as they provide an up-to-date situational image,” says Mäkelä. “During the implementation stage, supervisors can also view the photos and situational images in Infrakit on site, on their tablets.”

Construction of Jokeri Light Rail is a massive project that must take account of a wide range of issues. “For example, we create detours for the 550 bus service, and work on construction on streets, which can pose challenges for pedestrians and the flow of traffic at times. On the other hand, people have been understanding about certain restrictions and delays caused by changing traffic arrangements,” says Mäkelä.

Infrakit map view of the Jokeri Light Rail construction route at Oulunkylä, showing an aerial orthophoto with the light rail alignment overlaid in red across a residential and rail junction area in Helsinki.

Infrakit’s map view of Oulunkylä. Photo: Jokeri Light Rail

Jokeri Light Rail construction takes environmental issues seriously. Account is taken of important natural sites along the route. In addition to making natural and environmental surveys, the alliance has assessed the situation regarding issues such as the thick-shelled river mussel, flying squirrel habitats and alien species. In addition to considering biodiversity issues, construction must account for contaminated land and areas containing sulphate, for example.

Like the Jokeri Light Rail alliance, Infrakit is working to create more sustainable infrastructure construction. Infrakit Group’s CEO Teemu Kivimäki prefers to divide more sustainable infrastructure construction into three parts. “On individual level, we offer infrastructure builders the best possible tool for data management. Infrakit allows customers, designers and builders to access the same real-time view to make use of data for construction and quality assessment purposes. As all necessary construction data is available in a single cloud service, information becomes easier to share, and both time and material resources are saved.

Jokeri Light Rail construction site next to the Sello shopping centre. Photo: Jokeri Light Rail

At societal level, we can do our part to ensure that data management is properly handled, thereby minimising delays and unexpected extra costs in projects that may be small or indeed extensive, such as Jokeri Light Rail. This saves natural resources and is easier on end users, when construction times are not extended unnecessarily. From an ecological viewpoint, our core values include lower emissions, and high-quality, durable construction,” summarises Kivimäki.

See here for additional, regularly updated information about Jokeri Light Rail construction.

See how we turn clients’ projects into success stories

Explore our case studies
Thank you for your application! We will get back to you shortly.
Luftbild eines Straßen- und Knotenpunktprojekts

Kostenloser Leitfaden

10 Schritte, um Infrastrukturprojekte termingerecht und im Budget zu liefern

Vom Tramprojekt in Tampere über die E6 in Norwegen bis zur A9 in Österreich: So vermeiden führende Projektteams Nacharbeiten, verbessern die Zusammenarbeit und behalten die Kontrolle vom Angebot bis zur Übergabe.

Leitfaden kostenlos herunterladenNein danke
Flygfoto över ett väg- och trafikplatsprojekt

Gratis guide

10 steg för att leverera infrastrukturprojekt i tid och inom budget

Från Sveriges största anläggningsprojekt till E6 i Norge och A9 i Österrike: så minskar ledande team omarbete, förbättrar samarbetet och behåller kontrollen från anbud till överlämning.

Ladda ner gratis guideNej tack
Ilmakuva tie- ja eritasoliittymähankkeesta

Ilmainen opas

10 askelta infrahankkeiden toteuttamiseen aikataulussa ja budjetissa

Tampereen raitiotiestä Norjan E6-tiehen ja Itävallan A9-moottoritiehen: näin edelläkävijätiimit vähentävät uusintatyötä, parantavat yhteistyötä ja pitävät hankkeen hallinnassa tarjouksesta luovutukseen.

Lataa ilmainen opasEi kiitos
Flyfoto av et vei- og kryssprosjekt

Gratis veileder

10 steg for å levere infrastrukturprosjekter til rett tid og innenfor budsjettet

Fra trikken i Tampere til E6 i Norge og A9 i Østerrike: slik reduserer ledende team feil, forbedrer samarbeidet og beholder kontrollen fra anbud til overlevering.

Last ned veilederenNei takk
Aerial view of a road and interchange infrastructure project

Free guide

10 steps to deliver infrastructure projects on time and on budget

From the Tampere tram to Norway’s E6 and Austria’s A9: how leading teams reduce rework, improve collaboration and keep control from tender to handover.

Get the free guideNo thanks