On October 26, Nye Veier was able to open the last part of the new four-lane E6 motorway between Kolomoen and Moelv in Inland, Norway. Infrakit was used in the project.

According to Byggeindustrien (27.10.2020), Nye Veier’s Development director Øyvind Moshagen believes that both Veidekke and Nye Veier have good reason to be satisfied with the implementation of the Arnkvern-Moelv project.

“We have reduced the construction cost by 15-20 percent and Veidekke has ensured that the opening takes place approximately eight months earlier than originally planned. We are very happy with that”, says Moshagen to Byggeindustrien.

Read more about the use of Infrakit in the project here.

Read the original article in Norwegian published by Byggeindustrien here.

Linda Hakala
January 14, 2021

See how we turn clients’ projects into success stories

Explore our case studies
Thank you for your application! We will get back to you shortly.
Ilmakuva tie- ja eritasoliittymähankkeesta

Ilmainen opas

10 askelta infrahankkeiden toteuttamiseen aikataulussa ja budjetissa

Tampereen raitiotiestä Norjan E6-tiehen ja Itävallan A9-moottoritiehen: näin edelläkävijätiimit vähentävät uusintatyötä, parantavat yhteistyötä ja pitävät hankkeen hallinnassa tarjouksesta luovutukseen.

Lataa ilmainen opasEi kiitos
Flyfoto av et vei- og kryssprosjekt

Gratis veileder

10 steg for å levere infrastrukturprosjekter til rett tid og innenfor budsjettet

Fra trikken i Tampere til E6 i Norge og A9 i Østerrike: slik reduserer ledende team feil, forbedrer samarbeidet og beholder kontrollen fra anbud til overlevering.

Last ned veilederenNei takk
Aerial view of a road and interchange infrastructure project

Free guide

10 steps to deliver infrastructure projects on time and on budget

From the Tampere tram to Norway’s E6 and Austria’s A9: how leading teams reduce rework, improve collaboration and keep control from tender to handover.

Get the free guideNo thanks